Asked by Nathalie Almonte on May 03, 2024

verifed

Verified

Scanlon Inc.is considering Projects S and L,whose cash flows are shown below.These projects are mutually exclusive,equally risky,and not repeatable.If the decision is made by choosing the project with the higher IRR,how much value will be foregone? Note that under certain conditions,choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV.  WACC: 10.00%01234CFSS$2,050$750$760$770$780CFL−$4,300$1,500$1,518$1,536$1,554\begin{array}{ccccc}\text { WACC: } & 10.00 \% \\&0 & 1 & 2 & 3 & 4 \\\hline \mathrm{CFS}_{\mathrm{S}} &\$ 2,050 & \$ 750 & \$ 760 & \$ 770 & \$ 780 \\\mathrm{CF}_{\mathrm{L}} &-\$ 4,300 & \$ 1,500 & \$ 1,518 & \$ 1,536 & \$ 1,554\end{array} WACC: CFSSCFL10.00%0$2,050$4,3001$750$1,5002$760$1,5183$770$1,5364$780$1,554

A) $146.59
B) $154.30
C) $162.42
D) $178.67

IRR

Internal Rate of Return, the discount rate that makes the net present value (NPV) of all cash flows from a particular project equal to zero.

Mutually Exclusive

Situations or choices where the acceptance or selection of one necessarily excludes the other(s).

Value Foregone

The benefit given up by choosing one investment or action over another alternative; essentially the opportunity cost of a decision.

  • Enhance skills in applying the Net Present Value (NPV) framework for investment project assessment.
  • Scrutinize and juxtapose projects employing the Internal Rate of Return (IRR) framework.
verifed

Verified Answer

ZK
Zybrea KnightMay 03, 2024
Final Answer :
C
Explanation :
To determine the value that will be foregone by choosing the project with the higher IRR instead of the one with the higher NPV, we first need to calculate the NPV of both projects. The formula for NPV is: NPV=∑CFt(1+WACC)tNPV = \sum \frac{CF_t}{(1 + WACC)^t}NPV=(1+WACC)tCFt where CFtCF_tCFt is the cash flow at time ttt , and WACCWACCWACC is the weighted average cost of capital.For Project S: NPVS=−2050+750(1+0.1)1+760(1+0.1)2+770(1+0.1)3+780(1+0.1)4NPV_S = -2050 + \frac{750}{(1+0.1)^1} + \frac{760}{(1+0.1)^2} + \frac{770}{(1+0.1)^3} + \frac{780}{(1+0.1)^4}NPVS=2050+(1+0.1)1750+(1+0.1)2760+(1+0.1)3770+(1+0.1)4780NPVS=−2050+681.82+628.93+578.51+530.68=$470.94NPV_S = -2050 + 681.82 + 628.93 + 578.51 + 530.68 = \$470.94NPVS=2050+681.82+628.93+578.51+530.68=$470.94 For Project L: NPVL=−4300+1500(1+0.1)1+1518(1+0.1)2+1536(1+0.1)3+1554(1+0.1)4NPV_L = -4300 + \frac{1500}{(1+0.1)^1} + \frac{1518}{(1+0.1)^2} + \frac{1536}{(1+0.1)^3} + \frac{1554}{(1+0.1)^4}NPVL=4300+(1+0.1)11500+(1+0.1)21518+(1+0.1)31536+(1+0.1)41554NPVL=−4300+1363.64+1256.20+1153.82+1056.20=$530.86NPV_L = -4300 + 1363.64 + 1256.20 + 1153.82 + 1056.20 = \$530.86NPVL=4300+1363.64+1256.20+1153.82+1056.20=$530.86 The project with the higher NPV is Project L with an NPV of \$530.86, while Project S has an NPV of \$470.94. The value foregone by choosing the project with the higher IRR (assuming it's not Project L) instead of the one with the higher NPV is the difference in their NPVs: Value Foregone=NPVL−NPVS=$530.86−$470.94=$59.92Value\ Foregone = NPV_L - NPV_S = \$530.86 - \$470.94 = \$59.92Value Foregone=NPVLNPVS=$530.86$470.94=$59.92 However, none of the provided options match this calculation. Given the nature of the question, it seems there might have been a misunderstanding in the calculation process or the interpretation of the question. The correct approach involves calculating the NPVs as shown, but without the specific cash flows and IRRs provided, the exact value foregone cannot be determined from the given options. The explanation provided is based on the standard method for calculating NPV and determining value foregone between projects.