If any activity on the critical path is delayed, the completion of the project will be delayed by an equal amount.
Critical Path
The sequence of stages determining the minimum time needed to complete a project, identifying tasks that directly affect the project's duration.
Project Completion
The final phase of a project where all objectives have been achieved, and the project is closed out and handed over.
- Understand the impact of delays in activities on the critical path on overall project completion time.
Verified Answer
TW
Tiffany Wingert
Jun 21, 2024
Final Answer :
True
Explanation :
This is one of the fundamental principles of critical path analysis. Any delay in a critical path activity will result in a corresponding delay in the completion of the project, as there can be no floated time for tasks on the critical path.
Learning Objectives
- Understand the impact of delays in activities on the critical path on overall project completion time.
Related questions
The PERT Pessimistic Time Estimate Is an Estimate of the ...
The Standard Deviation of Project Duration Is the Average of ...
If You Have a Successfully Crowdfunded Product and You Know ...
Given the Project Within the Table Below CalculateA ...
The Network Below Represents a Project Being Analyzed by Critical ...