Asked by Kolby Finnie on Jun 20, 2024

verifed

Verified

If any activity on the critical path is delayed, the completion of the project will be delayed by an equal amount.

Critical Path

The sequence of stages determining the minimum time needed to complete a project, identifying tasks that directly affect the project's duration.

Project Completion

The final phase of a project where all objectives have been achieved, and the project is closed out and handed over.

  • Understand the impact of delays in activities on the critical path on overall project completion time.
verifed

Verified Answer

TW
Tiffany Wingert

Jun 21, 2024

Final Answer :
True
Explanation :
This is one of the fundamental principles of critical path analysis. Any delay in a critical path activity will result in a corresponding delay in the completion of the project, as there can be no floated time for tasks on the critical path.