Asked by Grace Ecton on Jun 28, 2024

verifed

Verified

The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.

Standard Deviation

A statistical measure that quantifies the variation or dispersion of a set of data points from its mean, indicating how spread out the data is.

Project Duration

The total time required to complete all phases of a project from initiation to closure.

Critical Path

The longest sequence of activities in a project plan that must be completed on time for the project to finish by its due date.

  • Acquire knowledge on how the length of activities impacts project planning and the crucial path.
verifed

Verified Answer

NG
Nicole GlymphJul 04, 2024
Final Answer :
False
Explanation :
The standard deviation of project duration is not necessarily the average of the standard deviation of all activities on the critical path. It depends on the complexity and interdependency of the project activities.