The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.

PERT Pessimistic Time

In the PERT project management technique, it is the longest time that a task is expected to take, considering potential delays and assuming that everything goes wrong.

Minimum Time

The shortest possible time in which a process or task can be completed, often considered in project planning and efficiency studies.

  • Understand the consequences of task duration on project timelines and the essential route.
verifed

Verified Answer

FE
Falon EvansJul 27, 2024
Final Answer :
False
Explanation :
The PERT pessimistic time estimate is an estimate of the maximum time an activity will require, not the minimum. The minimum time estimate is the optimistic time estimate.