Asked by Lauren Knight on Jul 26, 2024

verifed

Verified

The network below represents a project being analyzed by Critical Path Methods. Activity durations are indicated on the network. The network below represents a project being analyzed by Critical Path Methods. Activity durations are indicated on the network.   a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration? a. Identify the activities on the critical path.
b. What is the duration of the critical path?
c. Calculate the amount of slack time at activity H.
d. If activity I were delayed by ten time units, what would be the impact on the project duration?

Critical Path Methods

A project management technique that identifies the longest sequence of dependent tasks and allocates resources to minimize total project duration.

Slack Time

Free time for an activity.

Activity Durations

The estimated time periods that tasks or activities within a project are expected to take to complete.

  • Examine project tasks to pinpoint the essential sequence and compute the total time required for completion.
  • Compute and comprehend the importance of slack within the context of project management planning.
verifed

Verified Answer

NE
Nikki EstersJul 27, 2024
Final Answer :
(a) Critical activities are A-C-J-K.
(b) The critical path is 26 time units.
(c) Slack at H is 9 units.
(d) I has 11 units slack-a ten unit delay would have no impact on the project.
 Task  Early Start  Early Finish  Late Start  Late Finish  Slack  A 05050 B 03696 C 5165160 D 049139 E 3109166 F 410152111 G 37172114 H 4713169 I 1015212611 J 162216220 K 222622260 Project 26\begin{array} { | c | c | c | c | c | c | } \hline \text { Task } & \text { Early Start } & \text { Early Finish } & \text { Late Start } & \text { Late Finish } & \text { Slack } \\\hline \text { A } & 0 & 5 & 0 & 5 & 0 \\\hline \text { B } & 0 & 3 & 6 & 9 & 6 \\\hline \text { C } & 5 & 16 & 5 & 16 & 0 \\\hline \text { D } & 0 & 4 & 9 & 13 & 9 \\\hline \text { E } & 3 & 10 & 9 & 16 & 6 \\\hline \text { F } & 4 & 10 & 15 & 21 & 11 \\\hline \text { G } & 3 & 7 & 17 & 21 & 14 \\\hline \text { H } & 4 & 7 & 13 & 16 & 9 \\\hline \text { I } & 10 & 15 & 21 & 26 & 11 \\\hline \text { J } & 16 & 22 & 16 & 22 & 0 \\\hline \text { K } & 22 & 26 & 22 & 26 & 0 \\\hline & \text { Project } & 26 & & & \\\hline\end{array} Task  A  B  C  D  E  F  G  H  I  J  K  Early Start 00503434101622 Project  Early Finish 5316410107715222626 Late Start 06599151713211622 Late Finish 59161316212116262226 Slack 06096111491100