The predetermined overhead rate is closest to:

A) $34.06
B) $34.90
C) $34.67
D) $35.52

Predetermined Overhead Rate

An estimated charge per unit of activity used to allocate manufacturing overhead costs to products, calculated before the accounting period begins based on expected costs and activity levels.

  • Understand the role of the predetermined overhead rate in costing and decision-making processes.
verifed

Verified Answer

TM
Taylor McFarlandJun 23, 2024
Final Answer :
B
Explanation :
Predetermined overhead rate = Estimated total manufacturing overhead ÷ Estimated total amount of the allocation base
= $157,050 ÷ 4,500 machine-hours
= $34.90 per machine-hour