What is the early finish time for Activity I?
A) 76
B) 68
C) 84
D) 106
Early Finish Time
The earliest possible point in time when an activity or phase in a project can be completed, assuming all goes according to schedule.
- Organize project and activity schedules by drawing on project management practices.
Verified Answer
SL
Saravana LingamJul 10, 2024
Final Answer :
C
Explanation :
The early finish time for an activity in project management is calculated by adding the activity's duration to its early start time. Without specific details on the early start time or duration of Activity I, it's impossible to accurately determine its early finish time. However, given the options provided and assuming this is the correct answer based on a specific scenario provided elsewhere, C (84) would be the selected answer. This answer assumes specific project details that lead to this calculation.
Learning Objectives
- Organize project and activity schedules by drawing on project management practices.
Related questions
What Is the Early Finish Time for Activity O
The Network Below Represents a Project Being Analyzed by Critical ...
Given the Project Within the Table Below CalculateA ...
The Characteristics and Identifiers of an Activity Are Its _____
______________ ______________ Illustrate Schedules, Tasks and Activities Over a Specific ...