The additional time added to the schedule that can be used if a scheduled activity exceeds its estimated duration is called _____.

A) lag time
B) lead time
C) contingency time
D) forward pass
E) free float

Contingency Time

Additional time allocated within a project schedule to account for potential unforeseen delays.

  • Learn about the ideas of lead, lag, and float times and their significance in the context of project scheduling.
  • Familiarize yourself with the approach for altering and guiding the project plan to proficiently manage time.
verifed

Verified Answer

ZK
Zybrea KnightJun 07, 2024
Final Answer :
C
Explanation :
Contingency time is the additional time added to the schedule that can be used if a scheduled activity exceeds its estimated duration. Lag time refers to the delay between the start or end of one activity and the start or end of another activity. Lead time refers to the amount of time required to complete a task or project from start to finish. Forward pass is a method used in project scheduling to calculate the earliest possible start and finish date of each activity. Free float refers to the amount of time that an activity can be delayed without delaying the start of the next activity. Only contingency time fits the given definition.