Asked by Katherine Lupercio on Apr 25, 2024

The unit of time used to develop the activity duration is a function of:

A) the relationship dependence of project activities.
B) the skill level of the project team.
C) the level of detail needed by the user of the schedule.
D) the phase of the project.
E) the availability of project resources.

Activity Duration

The estimated or actual time it takes to complete a specific task or activity within a project.

Schedule

A detailed plan that outlines tasks, timings, durations, and dependencies in a project, guiding its timely execution.

  • Understand the concepts of lead, lag, and float times and their implications on project scheduling.