Asked by Samuella Agyemang on May 14, 2024

verifed

Verified

An) _____ is the soonest date an activity can begin as determined by the project start date and the durations of its predecessor activities.

A) early start date
B) negative float
C) free float
D) critical path
E) milestone

Early Start Date

The earliest date on which a task or project activity can begin, taking into account constraints and preceding activities.

  • Comprehend the basic principles of project scheduling and planning.
  • Acquire knowledge on the methods of modifying and administering the project timeline for effective time management.
verifed

Verified Answer

KD
Katrina DanticaMay 16, 2024
Final Answer :
A
Explanation :
The early start date is the soonest date an activity can begin as determined by the project start date and the durations of its predecessor activities. The other options do not fit the given definition. Negative float indicates that an activity is delayed beyond its scheduled completion date, free float refers to the amount of time an activity can be delayed without delaying the early start of its successor activities, critical path is the longest path of activities through the project network and milestone is a significant point or event in the project.