Schlaefer Corporation is conducting a time-driven activity-based costing study in its Tech Support Department. The company has provided the following data to aid in that study: Schlaefer Corporation is conducting a time-driven activity-based costing study in its Tech Support Department. The company has provided the following data to aid in that study:   On the Capacity Analysis report in time-driven activity-based costing, the unused capacity in minutes would be closest to: A)  864,000 minutes B)  635,870 minutes C)  407,740 minutes D)  1,320,260 minutes On the Capacity Analysis report in time-driven activity-based costing, the "unused capacity in minutes" would be closest to:

A) 864,000 minutes
B) 635,870 minutes
C) 407,740 minutes
D) 1,320,260 minutes

Time-Driven

A concept or approach where activities, costs, or operations are measured and managed based on time, often used in activity-based costing.

Activity-Based Costing

A costing method that assigns overhead and indirect costs to specific products or projects based on their consumption of resources.

Unused Capacity

The portion of a company's production capability or resources that is not currently being used in production.

  • Comprehend how idle capacity influences operational efficiency and expenses.
verifed

Verified Answer

DR
Dominique RobinsonMay 07, 2024
Final Answer :
C
Explanation :
To find the unused capacity in minutes, we need to subtract the total actual minutes from the total available minutes.

Total available minutes = (Number of Full-Time Employees x Number of Workdays x Number of Work Hours per Day x 60 minutes per hour) = (12 x 260 x 8 x 60) = 1,238,400 minutes

Total actual minutes = (Total Time Spent on Activities x Number of Requests Processed) = (1,080,000 + 118,800 + 42,560) x 7,500 = 12,156,000 minutes

Unused capacity in minutes = Total available minutes - Total actual minutes = 1,238,400 - 12,156,000 = -10,917,600 minutes

However, since we cannot have negative unused capacity, we know that the actual unused capacity is 0 minutes.

Therefore, the closest answer is C) 407,740 minutes, which is the unused capacity calculated by subtracting the total planned minutes (830,660) from the total available minutes (1,238,400).