Asked by Lourdes Orellana on Apr 26, 2024

verifed

Verified

Merritt Company is considering a new project that has a cost of $1,000,000,and the CFO set up the following simple decision tree to show its three most likely scenarios.Merritt could arrange with its work force and suppliers to cease operations at the end of Year 1 should it choose to do so,but to obtain this abandonment option,Merritt would have to make a payment to those parties.How much is the option to abandon worth (in thousands) to Merritt? WACC=11.5% Dollars in Thousands t=10 Prob =25% Prob =50%−$1,000 Prob =25% NPV this  Prob ×t=1t=2t=3 State  NPV $800.0$800.0$800.0$938.1$234.5$520.0$520.0$520.0$259.8$129.9−$200.0−$200.0−200.0−$1,484.5−$371.1\begin{array}{l}\begin{array}{lll}\mathrm{WACC}=11.5 \%& \text { Dollars in Thousands }\\&t=10\\\hline \text { Prob }=25 \% & \\\text { Prob }=50 \% & -\$ 1,000 \\\text { Prob }=25 \%\end{array}\begin{array}{lll} \text { NPV this } &\text { Prob } \times\\t=1 & t=2 & t=3 & \text { State } & \text { NPV } \\\hline \$ 800.0 & \$ 800.0 & \$ 800.0 & \$ 938.1 & \$ 234.5 \\\$ 520.0 & \$ 520.0 & \$ 520.0 & \$ 259.8 & \$ 129.9 \\-\$ 200.0 & -\$ 200.0 & -200.0 & -\$ 1,484.5&-\$ 371.1\end{array}\end{array}WACC=11.5% Prob =25% Prob =50% Prob =25% Dollars in Thousands t=10$1,000 NPV this t=1$800.0$520.0$200.0 Prob ×t=2$800.0$520.0$200.0t=3$800.0$520.0200.0 State $938.1$259.8$1,484.5 NPV $234.5$129.9$371.1

 Exp −$6.7 NPV \begin{array}{r}\text { Exp }-\$ 6.7 \\\text { NPV }\end{array} Exp $6.7 NPV 

A) $68.8
B) $72.5
C) $76.3
D) $80.1

Decision Tree

A form of scenario analysis in which different actions are taken in different scenarios.

Abandonment Option

Allows a company to reduce the capacity of its output in response to changing market conditions. This includes the option to contract production or abandon a project if market conditions deteriorate too much.

WACC

The Weighted Average Cost of Capital provides a measure for a company's cost of capital, where each type of capital is assigned a weight based on its proportion.

  • Comprehend the theory and process behind computing net present value (NPV) for decisions regarding project investments.
  • Evaluate the effects of project hazards and modifications in operations on the valuation of the project.
verifed

Verified Answer

DS
Dasani StallworthMay 01, 2024
Final Answer :
C
Explanation :
The option to abandon is worth the difference between the expected NPV without the option and the cost of the project. Without the option, the expected NPV is -$6.7 thousand. With the option, the project would not proceed in the worst-case scenario (-$371.1 thousand NPV), improving the expected outcome. The value of the option is the difference needed to reach a zero NPV from -$6.7 thousand, which is approximately $76.3 thousand.