Which of the following statements concerning CPM activities is false?

A) The early finish of an activity is the early start of that activity plus its duration.
B) The late finish is the earliest of the late start times of all successor activities.
C) The late start of an activity is its late finish less its duration.
D) The late finish of an activity is the earliest late start of all preceding activities.
E) The early start of an activity is the latest early finish of all preceding activities.

Early Finish

In project management, the earliest possible point in time when a task or project phase can be completed, assuming all goes according to plan.

Late Start

The latest possible time a task can begin without delaying the project completion date in project management.

Activity Duration

The total length of time required to complete a specific task or activity from start to finish.

  • Familiarize oneself with the significance and deployment of critical path analysis in project organization and implementation.
verifed

Verified Answer

JR
Jonah RuskinJul 05, 2024
Final Answer :
D
Explanation :
The late finish of an activity is determined by the latest of the early start times of its successor activities, not the earliest late start of all preceding activities. This statement misrepresents how the late finish time is calculated in the Critical Path Method (CPM).