Asked by Devin Usher on May 07, 2024

verifed

Verified

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D = 5, E = 4, F = 9.

A) The critical path is D-E-F, duration 18.
B) The critical path is D-F, duration 14.
C) Slack at D is 4 units.
D) Slack at E is 4 units.
E) The network has two critical paths.

Critical Path

The longest sequence of activities in a project plan which must be completed on time for the project to finish by its due date.

Immediate Predecessor

Refers to an immediately preceding task or step that must be concluded before the next one can start, in a sequence of operations or processes.

Activity Durations

The estimated or actual amount of time needed to complete an activity or task in project management.

  • Understand the importance and use of critical path analysis in the planning and execution of projects.
verifed

Verified Answer

MG
Mikhial GuggemosMay 13, 2024
Final Answer :
A
Explanation :
The critical path is the longest path, which in this case is D-E-F with a duration of 18.

Answer: C
Slack at a particular activity is the amount of time the activity can be delayed without impacting the project duration. Slack at D can be calculated as follows: Slack at D = (EF - D) - (LF - D) = (18 - 5) - (18 - 9) = 4.

Answer: D
Slack at E can be calculated as follows: Slack at E = (LF - E) - (EF - E) = (18 - 4) - (14 - 4) = 4.

Answer: E
The network has only one critical path, which is D-E-F. There cannot be two critical paths in a simple CPM network.