The total overhead applied to Product A7 under activity-based costing is closest to:

A) $373,632
B) $115,524
C) $241,548
D) $413,664

Activity-Based Costing

A costing methodology that assigns costs to products or services based on the activities and resources that go into their production or provision, aiming for more accurate cost allocation.

  • Compute the overhead apportioned to designated products via activity-based costing practices.
verifed

Verified Answer

SC
Sapna ChandanJun 24, 2024
Final Answer :
D
Explanation :
Computation of activity rates: Computation of activity rates:   Computation of the overhead cost under activity-based costing.   Reference: CH04-Ref12 Overturf, Inc., manufactures and sells two products: Product Y1 and Product Y0.Data concerning the expected production of each product and the expected total direct labor-hours (DLHs)required to produce that output appear below:   The direct labor rate is $27.50 per DLH.The direct materials cost per unit is $106.10 for Product Y1 and $168.40 for Product Y0. The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:  Computation of the overhead cost under activity-based costing. Computation of activity rates:   Computation of the overhead cost under activity-based costing.   Reference: CH04-Ref12 Overturf, Inc., manufactures and sells two products: Product Y1 and Product Y0.Data concerning the expected production of each product and the expected total direct labor-hours (DLHs)required to produce that output appear below:   The direct labor rate is $27.50 per DLH.The direct materials cost per unit is $106.10 for Product Y1 and $168.40 for Product Y0. The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:  Reference: CH04-Ref12
Overturf, Inc., manufactures and sells two products: Product Y1 and Product Y0.Data concerning the expected production of each product and the expected total direct labor-hours (DLHs)required to produce that output appear below: Computation of activity rates:   Computation of the overhead cost under activity-based costing.   Reference: CH04-Ref12 Overturf, Inc., manufactures and sells two products: Product Y1 and Product Y0.Data concerning the expected production of each product and the expected total direct labor-hours (DLHs)required to produce that output appear below:   The direct labor rate is $27.50 per DLH.The direct materials cost per unit is $106.10 for Product Y1 and $168.40 for Product Y0. The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:  The direct labor rate is $27.50 per DLH.The direct materials cost per unit is $106.10 for Product Y1 and $168.40 for Product Y0.
The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity: Computation of activity rates:   Computation of the overhead cost under activity-based costing.   Reference: CH04-Ref12 Overturf, Inc., manufactures and sells two products: Product Y1 and Product Y0.Data concerning the expected production of each product and the expected total direct labor-hours (DLHs)required to produce that output appear below:   The direct labor rate is $27.50 per DLH.The direct materials cost per unit is $106.10 for Product Y1 and $168.40 for Product Y0. The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity: