The predetermined overhead rate is closest to:

A) $9.39 per labor-hour
B) $9.22 per labor-hour
C) $13.15 per labor-hour
D) $12.91 per labor-hour

Predetermined Overhead Rate

The predetermined overhead rate is a rate used to allocate manufacturing overhead costs to products or job orders, based on estimated overhead costs and activity levels.

  • Find the predetermined rate for overhead costs.
verifed

Verified Answer

SM
Shaun MichaelMay 23, 2024
Final Answer :
B
Explanation :
To calculate the predetermined overhead rate, we need to divide the estimated total manufacturing overhead costs by the estimated total labor hours.
Predetermined overhead rate = Estimated total manufacturing overhead costs ÷ Estimated total labor hours
From the data given,
Estimated total manufacturing overhead costs = $650,800
Estimated total labor hours = 70,400
Therefore, the predetermined overhead rate = $650,800 ÷ 70,400 = $9.22 per labor-hour.
Therefore, the best choice is B.
Explanation :
Predetermined overhead rate = $451,780/49,000 labor-hours = $9.22 per labor-hour