Asked by Kattelin Crocker on May 04, 2024

verifed

Verified

The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $3,044. A total of 46 direct labor-hours and 104 machine-hours were worked on the job. The direct labor wage rate is $15 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine-hour. The total cost for the job on its job cost sheet would be:

A) $4,332
B) $3,734
C) $3,072
D) $5,086

Direct Materials Cost

The cost of raw materials and components that are directly used in the production of a product.

Direct Labor-hours

Direct labor-hours are the total time workers spend on producing a particular unit of goods or services.

Predetermined Overhead Rate

An estimated rate used to allocate manufacturing overhead costs to individual units of production based on a certain activity base, such as labor hours or machine hours.

  • Figure out the entire cost of a project through job cost sheet information, taking into account materials, labor, and overhead that is applied.
  • Appraise the level of overhead assigned to a job rooted in predetermined overhead rates.
verifed

Verified Answer

RM
Rebecca MeyerMay 07, 2024
Final Answer :
D
Explanation :
Direct materials cost = $3,044
Direct labor cost = 46 hours x $15 per hour = $690
Manufacturing overhead cost = 104 machine-hours x $13 per machine-hour = $1,352

Total cost for the job = Direct materials cost + Direct labor cost + Manufacturing overhead cost
= $3,044 + $690 + $1,352
= $5,086

Therefore, the total cost for the job on its job cost sheet would be $5,086, which is option D.