Asked by Chris Hughes on Jul 01, 2024

verifed

Verified

The network analysis method that allows activity times to vary is ________.

Network Analysis Method

is a systematic approach used in project management that involves mapping out a project in terms of nodes (activities) and links (relationships), to identify the most efficient sequence of operations.

  • Master the fundamentals and practical aspects of applying Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) for project management.
verifed

Verified Answer

JJ
Juan José Guerrero BoteroJul 03, 2024
Final Answer :
PERT or Program Evaluation and Review Technique