What is the basic difference between PERT and CPM?

PERT

Short for Program Evaluation and Review Technique, a project management tool used to schedule, organize, and coordinate tasks within a project.

CPM

Critical Path Method, a project management tool used to schedule, organize, and coordinate tasks within a project.

  • Identify the differences and similarities in objectives and calculation methodologies between the Critical Path Method (CPM) and PERT.
verifed

Verified Answer

MD
Muhammad Dzul HaqiemMay 13, 2024
Final Answer :
The basic difference between PERT and CPM is that PERT requires three time estimates of activity completion time, whereas CPM uses only a single estimate.