The materials price variance for June is:

A) $2,140 U
B) $2,140 F
C) $1,820 U
D) $1,820 F

Materials Price Variance

The difference between the actual cost of materials purchased and the expected cost, based on standard prices.

  • Become adept at analyzing and determining the differences in material cost variances.
verifed

Verified Answer

MO
Michael Osborne

Mar 10, 2024

Final Answer :
B
Explanation :
The materials price variance is calculated as (actual price - standard price) x actual quantity. From the information given in the question, we have: actual price = $8.20, standard price = $7.00, actual quantity = 8,400 lbs.

Therefore, the materials price variance for June is ($8.20 - $7.00) x 8,400 = $2,140 F.
Explanation :
AQ × AP = $40,660
Materials price variance = (AQ × AP)− (AQ × SP)
= ($40,660)− (21,400 ounces × $2.00 per ounce)
= $40,660 − $42,800
= $2,140 F