Asked by Elizabeth Ridgeway on May 29, 2024

verifed

Verified

Teasley Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours.The company based its predetermined overhead rate for the current year on 70,000 machine-hours, total fixed manufacturing overhead cost of $630,000, and a variable manufacturing overhead rate of $3.40 per machine-hour.Job X159 was recently completed.The job cost sheet for the job contained the following data: Teasley Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours.The company based its predetermined overhead rate for the current year on 70,000 machine-hours, total fixed manufacturing overhead cost of $630,000, and a variable manufacturing overhead rate of $3.40 per machine-hour.Job X159 was recently completed.The job cost sheet for the job contained the following data:   Required: Calculate the total job cost for Job X159. Required:
Calculate the total job cost for Job X159.

Machine-Hours

A unit of measure indicating the duration machines are in operation in a manufacturing setting, critical in cost allocation and efficiency studies.

Predetermined Overhead Rate

A rate used to apply manufacturing overhead to products or job orders, calculated before the period begins based on estimated costs.

Variable Manufacturing Overhead

Costs incurred during the production process that vary with the level of production, such as utilities for the manufacturing plant.

  • Calculate the total expenditure of a job by applying the tenets of job-order costing.
verifed

Verified Answer

ZK
Zybrea KnightJun 04, 2024
Final Answer :
Estimated total manufacturing overhead cost = Estimated total fixed manufacturing overhead cost + (Estimated variable overhead cost per unit of the allocation base × Estimated total amount of the allocation base)= $630,000 + ($3.40 per machine-hour × 70,000 machine-hours)= $630,000 + $238,000 = $868,000
Predetermined overhead rate = Estimated total manufacturing overhead cost ÷ Estimated total amount of the allocation base = $868,000 ÷ 70,000 machine-hours = $12.40 per machine-hour
Overhead applied to a particular job = Predetermined overhead rate x Amount of the allocation base incurred by the job = $12.40 per machine-hour × 200 machine-hours = $2,480 Estimated total manufacturing overhead cost = Estimated total fixed manufacturing overhead cost + (Estimated variable overhead cost per unit of the allocation base × Estimated total amount of the allocation base)= $630,000 + ($3.40 per machine-hour × 70,000 machine-hours)= $630,000 + $238,000 = $868,000 Predetermined overhead rate = Estimated total manufacturing overhead cost ÷ Estimated total amount of the allocation base = $868,000 ÷ 70,000 machine-hours = $12.40 per machine-hour Overhead applied to a particular job = Predetermined overhead rate x Amount of the allocation base incurred by the job = $12.40 per machine-hour × 200 machine-hours = $2,480