Asked by Tishera Brooks on Jul 28, 2024

verifed

Verified

Milar Corporation makes a product with the following standard costs: Milar Corporation makes a product with the following standard costs:   In January the company produced 2,000 units using 16,060 pounds of the direct material and 210 direct labor-hours. During the month, the company purchased 16,900 pounds of the direct material at a cost of $65,910. The actual direct labor cost was $4,473 and the actual variable overhead cost was $756.The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased.The labor rate variance for January is: A)  $260 Unfavorable B)  $273 Unfavorable C)  $260 Favorable D)  $273 Favorable In January the company produced 2,000 units using 16,060 pounds of the direct material and 210 direct labor-hours. During the month, the company purchased 16,900 pounds of the direct material at a cost of $65,910. The actual direct labor cost was $4,473 and the actual variable overhead cost was $756.The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased.The labor rate variance for January is:

A) $260 Unfavorable
B) $273 Unfavorable
C) $260 Favorable
D) $273 Favorable

Direct Materials

Ingredients that are specifically identifiable in the creation of a certain product.

Direct Labor-Hours

The broad sum of hours dedicated by workers directly in the manufacturing workflow.

Variable Overhead

Indirect production costs that vary with the level of output, such as utilities for a manufacturing plant.

  • Execute computations and investigate variances associated with direct labor's rate and efficiency aspects.
verifed

Verified Answer

KB
Kayla Brown VoilesAug 04, 2024
Final Answer :
B
Explanation :
To calculate the labor rate variance, we need to first calculate the actual labor rate per hour:
Actual Labor Rate = Actual Labor Cost / Actual Hours
Actual Labor Rate = $4,473 / 210 hours
Actual Labor Rate = $21.30 per hour

Next, we need to calculate the standard labor rate per hour:
Standard Labor Rate = Standard Labor Cost / Standard Hours
Standard Labor Rate = $8.00 / 0.50 hours
Standard Labor Rate = $16.00 per hour

Finally, we can calculate the labor rate variance:
Labor Rate Variance = (Actual Hours x (Actual Labor Rate - Standard Labor Rate))
Labor Rate Variance = 210 hours x ($21.30 - $16.00)
Labor Rate Variance = 210 hours x $5.30
Labor Rate Variance = $1,113

Since the labor rate variance is unfavorable (the actual rate is higher than the standard rate), the answer is B) $273 Unfavorable.