Asked by Sandra Belgarde on May 26, 2024

verifed

Verified

If the numbers of sp2 and sp3 hybrid gaming consoles produced each day are denoted as X1 and X2 respectively,the function that describes the production department's labor constraint for a week is ________.

A) 2X1 + 1.5X2 ≥ 875
B) 9X1 + 8X2 ≤ 3500
C) 2X1 + 1.5X2 ≤ 875
D) 9X1 + 8X2 ≥ 3500

Labor Hours

The total number of hours worked by employees within a specific time period, often used to measure productivity or to calculate labor costs.

Production Department

A division within a company responsible for the actual manufacturing or creation of goods and services.

Labor Constraint

Restrictions or limitations on the availability or use of workers that can affect production or service delivery.

  • Comprehend and calculate labor and production requirements and constraints within given scenarios.
verifed

Verified Answer

MT
Minh Tân Nguy?nMay 29, 2024
Final Answer :
C
Explanation :
The labor constraint of production department can be derived from the given information as follows:
For producing one sp2 model, 2 labor hours are required for production department.
So, for producing X1 sp2 models in a week, the labor hours required by production department will be:
2*7*X1 = 14X1
Similarly, for producing one sp3 model,1.5 labor hours are required for production department.
So, for producing X2 sp3 models in a week, the labor hours required by production department will be:
1.5*7*X2 = 10.5X2
Therefore, the production department's labor constraint for a week will be:
14X1 + 10.5X2 ≤ total labor hours in a week
= 25*7*5 (as 25 workers work 7 hours per day and company operates 5 days per week)
= 875