Your firm has a contract to make 20 specialty lenses for night vision equipment. The first one took 40 hours. Learning is expected at the 85% rate. How long will it take to finish all 20 units?

Learning Rate

The speed at which a person acquires knowledge or skills, often analyzed in the context of cost reductions or performance improvement over time.

Specialty Lenses

Custom or uniquely designed lenses tailored for specific purposes, such as correcting particular vision issues or enhancing performance in certain activities.

  • Determine total and average time for production runs using learning curves.
verifed

Verified Answer

ZK
Zybrea KnightMay 05, 2024
Final Answer :
The best solution method uses Table E.3 in the text. For 85% learning, total time for 20 units, the table factor is 12.402. Total time for all 20 units is 12.402 ∗ 40 = 496.1 hours.