Which one of the following types of costs should not be included in the cost of a building?

A) costs of remodeling and reconditioning
B) excavation costs
C) unanticipated costs resulting from the condition of the land
D) unanticipated construction costs, such as strike or fire losses

Unanticipated Costs

Expenses that were not planned or predicted in the budgeting process, often leading to budget overruns.

Remodeling

The process of making improvements or alterations to a building's structure or design, often to update or increase its value.

Excavation Costs

Expenses associated with the removal of earth to make way for construction or mining operations.

  • Pinpoint and keep a record of the procurement cost for assets, production facilities, and machinery.
verifed

Verified Answer

ZK
Zybrea KnightJul 06, 2024
Final Answer :
D
Explanation :
Unanticipated construction costs, such as strike or fire losses, are not expected and therefore cannot be included in the initial cost of the building. The other options, costs of remodeling and reconditioning, excavation costs, and unanticipated costs resulting from the condition of the land, are all anticipated costs that would be factored into the total cost of the building.