Which of the following would be considered a material breach of a contract?
A) Partial performance that omits some essential part of the contract.
B) Delivery of 50 chairs in a contract that calls for 100 chairs.
C) An intentional breach of the contract.
D) All of these would be material breaches.
Material Breach
A significant violation of a contract that harms the interests of the other party involved, justifying the termination of the agreement.
- Understand the notion of material breach and its repercussions for individuals bound by a contract.
Verified Answer
ZK
Zybrea KnightJul 04, 2024
Final Answer :
D
Explanation :
- A) Partial performance that omits some essential part of the contract can be considered a material breach because it fails to fulfill the agreed-upon terms of the contract.
- B) Delivery of 50 chairs in a contract that calls for 100 chairs can also be considered a material breach because it fails to provide the full quantity of goods or services as specified in the contract.
- C) An intentional breach of the contract is even more serious and clearly constitutes a material breach because it shows a deliberate and willful disregard for the terms of the agreement. Therefore, all of these options would be considered material breaches of a contract.
- B) Delivery of 50 chairs in a contract that calls for 100 chairs can also be considered a material breach because it fails to provide the full quantity of goods or services as specified in the contract.
- C) An intentional breach of the contract is even more serious and clearly constitutes a material breach because it shows a deliberate and willful disregard for the terms of the agreement. Therefore, all of these options would be considered material breaches of a contract.
Learning Objectives
- Understand the notion of material breach and its repercussions for individuals bound by a contract.
Related questions
Hygrade Fruit Juice Co ...
List the Elements Required for Substantial Performance,and Explain the Effect ...
A[n] ________ Discharges the Nonbreaching Party from His or Her ...
________ Damages Are Designed to Put the Plaintiff in the ...
When a Contracting Party Refuses to Complete the Contract Before ...