When a contracting party refuses to complete the contract before the actual time of performance,it is called a(n) ________.

A) preemptive strike
B) anticipatory repudiation
C) ante-breach
D) advance renunciation
E) executory renunciation

Anticipatory Repudiation

Occurs when one party involved in a contract indicates in advance that they will not fulfill their contractual obligations, allowing the other party to take legal action.

Preemptive Strike

A military or strategic attack intended to neutralize a perceived imminent threat from an opponent before that threat can harm the party making the strike.

  • Investigate the consequences of material breaches and breaches of expectation on obligations under a contract.
verifed

Verified Answer

AA
Arinn ArnoldMay 25, 2024
Final Answer :
B
Explanation :