When building a house or constructing an airplane that must be completed by a certain date, which type of scheduling should be used?

A) forward scheduling
B) backward scheduling
C) horizontal scheduling
D) vertical scheduling

Backward Scheduling

A planning method that starts with the end goal or deadline and works backwards to determine the timing of preceding activities.

Constructing Airplane

The engineering and assembling processes involved in building aircraft.

Certain Date

A specific, identified day in the calendar on which an event is scheduled to take place or a deadline is set.

  • Identify different methods of scheduling and understand their significance in improving productivity and effectiveness.
verifed

Verified Answer

ZK
Zybrea KnightMay 05, 2024
Final Answer :
B
Explanation :
Backward scheduling is used when a project has a fixed end date. It involves planning the necessary tasks by starting from the project's deadline and working backwards to determine when work should start. This approach ensures that the project is completed by the specific due date, making it suitable for constructions like houses or airplanes that have a set completion date.