Asked by Brendan Lorenzana on Jul 05, 2024

verifed

Verified

The _____ is typically a written document that defines what work will be accomplished by the end of the project.

A) work breakdown structure
B) project logic diagram
C) milestone schedule
D) ballpark estimate
E) scope of work

Written Document

A material record containing information or evidence, captured in written form.

Work Accomplished

The actual progress or achievements made on a project or task, often measured against planned objectives.

Scope Of Work

A detailed document or section of a document that outlines all aspects of what needs to be accomplished in a project.

  • Understand the procedure and value of delineating a project's extent, timeline, and cost approximations.
verifed

Verified Answer

JR
Jessica RamosJul 09, 2024
Final Answer :
E
Explanation :
The scope of work is a written document that outlines the specific deliverables and objectives that the project will achieve. It is an essential part of project planning and sets the direction for the entire project. The work breakdown structure breaks down the scope of work into smaller, manageable tasks, while the project logic diagram shows the relationships between project tasks. The milestone schedule outlines key dates and events throughout the project, and the ballpark estimate provides a rough cost estimate for the project.