A layered description of the work with increasing detail in each layer is known as a _____.
A) work breakdown structure
B) step change
C) ballpark estimate
D) project execution plan
E) project logic diagram
Work Breakdown Structure
A hierarchical decomposition of a project into smaller components or tasks, making it easier to manage and execute.
Step Change
A significant and sudden change in performance or productivity, typically for the better.
Ballpark Estimate
An approximate calculation or guess made with limited information, usually at an early stage to provide a rough idea of the expected cost or extent of a project or task.
- Acknowledge the significance and methodology behind establishing the scope, timetable, and financial projections of a project.
Verified Answer
Learning Objectives
- Acknowledge the significance and methodology behind establishing the scope, timetable, and financial projections of a project.
Related questions
The Conceptual Estimate Is Developed with the Least Amount of ...
According to the Project Management Institute PMI), Project Management Is ...
The _____ Is Typically a Written Document That Defines What ...
__________ Refer to One-Time Activities That Have Clear Beginning and ...
Which of the Following Is the First Step in Managing ...