Tanouye Corporation keeps careful track of the time required to fill orders.Data concerning a particular order appear below: The throughput time was:
A) 4.1 hours
B) 12.9 hours
C) 25.6 hours
D) 21.5 hours
Throughput Time
The total time taken to manufacture a product from start to finish, including processing, waiting, and transport times.
- Analyze and compute the time taken for processes, including throughput and delivery cycle times.
Verified Answer
MB
maria BarraganJul 26, 2024
Final Answer :
B
Explanation :
The throughput time includes the time it took to process the order (4.5 hours), the wait time in the queue (5.5 hours), and the time it took to receive the order (2.9 hours). Therefore, the total throughput time is:
4.5 hours + 5.5 hours + 2.9 hours = 12.9 hours
Thus, the correct choice is B.
4.5 hours + 5.5 hours + 2.9 hours = 12.9 hours
Thus, the correct choice is B.
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 1.6 hours + 0.4 hours + 2.1 hours + 8.8 hours = 12.9 hours
= 1.6 hours + 0.4 hours + 2.1 hours + 8.8 hours = 12.9 hours
Learning Objectives
- Analyze and compute the time taken for processes, including throughput and delivery cycle times.