The throughput time was:

A) 30.6 hours
B) 3.2 hours
C) 27.4 hours
D) 12.3 hours

Throughput Time

The amount of time required for a product to pass through a manufacturing process from start to finish.

  • Comprehend the methodology and importance of determining delivery cycle time.
verifed

Verified Answer

HM
Haley McElroyJun 09, 2024
Final Answer :
D
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 1.1 hours + 0.1 hours + 2.0 hours + 9.1 hours = 12.3 hours