Schapp Corporation keeps careful track of the time required to fill orders.The times recorded for a particular order appear below: Schapp Corporation keeps careful track of the time required to fill orders.The times recorded for a particular order appear below:   The throughput time was: A) 11.3 hours B) 21.7 hours C) 17.2 hours D) 4.5 hours The throughput time was:

A) 11.3 hours
B) 21.7 hours
C) 17.2 hours
D) 4.5 hours

Throughput Time

The total time taken for a product to be completed from start to finish, including processing, waiting, and transport times.

  • Comprehend and implement the principle of manufacturing cycle efficiency (MCE).
verifed

Verified Answer

ZK
Zybrea KnightJun 11, 2024
Final Answer :
A
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 1.5 hours + 0.4 hours + 2.6 hours + 6.8 hours = 11.3 hours