Schapp Corporation keeps careful track of the time required to fill orders.The times recorded for a particular order appear below: The throughput time was:
A) 11.3 hours
B) 21.7 hours
C) 17.2 hours
D) 4.5 hours
Throughput Time
The total time taken for a product to be completed from start to finish, including processing, waiting, and transport times.
- Comprehend and implement the principle of manufacturing cycle efficiency (MCE).
Verified Answer
ZK
Zybrea KnightJun 11, 2024
Final Answer :
A
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 1.5 hours + 0.4 hours + 2.6 hours + 6.8 hours = 11.3 hours
= 1.5 hours + 0.4 hours + 2.6 hours + 6.8 hours = 11.3 hours