Product X requires 30 minutes of machining on a lathe, and product Y requires 45 minutes of machining. If the lathe was operated for 60.5 hours last week for machining a combined total of 93 units of Products X and Y, how many units of each product were produced?

Machining

A manufacturing process involving the cutting, shaping, or finishing of metal or other materials with machine tools.

Lathe

A lathe is a machine tool used to shape metal, wood, or other materials by rotating the workpiece against a cutting tool.

  • Implement the principle of time and work in examining issues related to production and operations.
verifed

Verified Answer

KS
Kiara SlaughterMay 29, 2024
Final Answer :
37 units of X and 56 units of Y