Asked by carolette mckenzie on May 27, 2024

verifed

Verified

Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year: Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year:   The following were the actual results:   Calculate the amount of variable overhead efficiency variance. A)  $25 000 favourable B)  $25 000 unfavourable C)  $15 000 favourable D)  $15 000 unfavourable
The following were the actual results: Hamilton Pty Ltd uses a standard costing system for product costing. The company uses direct labour hours as the cost driver to apply overhead costs. The following amounts were budgeted for the year:   The following were the actual results:   Calculate the amount of variable overhead efficiency variance. A)  $25 000 favourable B)  $25 000 unfavourable C)  $15 000 favourable D)  $15 000 unfavourable
Calculate the amount of variable overhead efficiency variance.

A) $25 000 favourable
B) $25 000 unfavourable
C) $15 000 favourable
D) $15 000 unfavourable

Standard Costing System

A cost accounting method that assigns expected costs to products in order to estimate the cost of production and help with budget planning.

Direct Labour Hours

The total hours worked directly on a specific job or task by employees, often used to allocate labor costs to products or services.

  • Comprehend the elements contributing to discrepancies in standard costing, such as variations in variable overhead efficiency and fixed overhead volume variances.
verifed

Verified Answer

KS
Kaylie SorensenJun 02, 2024
Final Answer :
D
Explanation :
Variable overhead efficiency variance = (actual activity – standard activity) x standard rate

Actual activity = 20,000 hours
Standard activity = 22,000 hours
Standard rate per hour = $5

Variable overhead efficiency variance = (20,000 – 22,000) x $5 = $-10,000 or $10,000 unfavourable

Therefore, the answer is D) $15,000 unfavourable is incorrect, and B) $25,000 unfavourable is correct.