Find the sequence for the priority rules of
a. LPT
b. SPT
c. EDD
Given the table below and the fact that today is the 1st
 job  Process Time  Due Date  A 320 B 42 C 25 D 916\begin{array} { | l | l | l | } \hline \text { job } & \text { Process Time } & \text { Due Date } \\\hline \text { A } & 3 & 20 \\\hline \text { B } & 4 & 2 \\\hline \text { C } & 2 & 5 \\\hline \text { D } & 9 & 16 \\\hline\end{array} job  A  B  C  D  Process Time 3429 Due Date 202516

Priority Rules

Guidelines used in manufacturing and project management to determine the order in which tasks or jobs should be executed based on their importance.

Process Time

The duration it takes to complete a specific task or operation from start to finish in a manufacturing or service process.

LPT

Shortest Processing Time, a rule used in job sequencing to minimize the total processing time by scheduling jobs in ascending order of their processing times.

  • Learn the pivotal dispatching norms and their application in agenda setting.
  • Select the ideal scheduling option contingent on established performance indicators.
verifed

Verified Answer

NA
norhan ahmedJun 09, 2024
Final Answer :
a. DBAC
b. CABS
c. BCDA