A firm that specializes in desktop publishing for local charities has agreed to take on the following jobs. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. All dates are specified as days from Today.
 Time  Due Date  Tob 1 2025 Tob 2 1520 Tob 3 716 Job 4 2550 Tob 5 3133 Job 6 4355\begin{array} { | l | l | l | } \hline & \text { Time } & \text { Due Date } \\\hline \text { Tob 1 } & 20 & 25 \\\hline \text { Tob 2 } & 15 & 20 \\\hline \text { Tob 3 } & 7 & 16 \\\hline \text { Job 4 } & 25 & 50 \\\hline \text { Tob 5 } & 31 & 33 \\\hline \text { Job 6 } & 43 & 55 \\\hline\end{array} Tob 1  Tob 2  Tob 3  Job 4  Tob 5  Job 6  Time 20157253143 Due Date 252016503355 a. Complete the following table. Show your supporting calculations below.
b. Which dispatching rule has the best score for flow time?
c. Which dispatching rule has the best score for work-in-process (jobs in the system)?
d. Which dispatching rule has the best score for lateness?
 Dispatching  Rule  Job Sequence  Average  Flow Time  Average  Number of  Jobs  Average  Lateness  FCFS  EDD  SPT  LPT \begin{array} { | l | c | c | c | c | } \hline \begin{array} {c } \text { Dispatching } \\\text { Rule }\end{array} & \text { Job Sequence } & \begin{array} { c } \text { Average } \\\text { Flow Time }\end{array} & \begin{array} { c } \text { Average } \\\text { Number of } \\\text { Jobs }\end{array} & \begin{array} { c } \text { Average } \\\text { Lateness }\end{array} \\\hline \text { FCFS } & & & & \\\hline \text { EDD } & & & & \\\hline \text { SPT } & & & & \\\hline \text { LPT } & & & & \\\hline\end{array} Dispatching  Rule  FCFS  EDD  SPT  LPT  Job Sequence  Average  Flow Time  Average  Number of  Jobs  Average  Lateness 

Dispatching Rule

A guideline or criterion used to determine the scheduling and order in which jobs should be processed in manufacturing or service operations.

Flow Time

The time taken for a unit to move through an entire system or process, from start to finish.

Work-In-Process

Items or materials that are in the stage of production but have not yet been completed.

  • Familiarize oneself with the essential aspects of dispatching and their application in planning.
  • Analyze the comparative effectiveness of various scheduling directives regarding average flow time, work-in-process, lateness, and makespan.
  • Find the leading scheduling technique tailored to specific performance expectations.
verifed

Verified Answer

BC
Bryleigh CollinsMay 21, 2024
Final Answer :
(a) The table of results appears below. A supporting table for each dispatch rule also follows.
 Dispatching  Rule  Job Sequence  Average  Flow Time  Average  Number of  Jobs  Average  Lateness  FCFS 1−2−3−4−5−667.22.8634.8 EDD 3−2−1−5−4−663.82.7132.2 SPT 3−2−1−4−5−662.82.6731.2 LPT 6−5−4−1−2−3101.74.3370.5\begin{array} { | l | c | c | c | c | } \hline \begin{array} { c } \text { Dispatching } \\\text { Rule }\end{array} & \text { Job Sequence } & \begin{array} { c } \text { Average } \\\text { Flow Time }\end{array} & \begin{array} { c } \text { Average } \\\text { Number of } \\\text { Jobs }\end{array} & \begin{array} { c } \text { Average } \\\text { Lateness }\end{array} \\\hline \text { FCFS } & 1 - 2 - 3 - 4 - 5 - 6 & 67.2 & 2.86 & 34.8 \\\hline \text { EDD } & 3 - 2 - 1 - 5 - 4 - 6 & 63.8 & 2.71 & 32.2 \\\hline \text { SPT } & 3 - 2 - 1 - 4 - 5 - 6 & 62.8 & 2.67 & 31.2 \\\hline \text { LPT } & 6 - 5 - 4 - 1 - 2 - 3 & 101.7 & 4.33 & 70.5 \\\hline\end{array} Dispatching  Rule  FCFS  EDD  SPT  LPT  Job Sequence 123456321546321456654123 Average  Flow Time 67.263.862.8101.7 Average  Number of  Jobs 2.862.712.674.33 Average  Lateness 34.832.231.270.5 (b,c,d) The SPT rule is best for flow time, for average jobs in system, and for lateness.  FCFS  Time  Due  Date  Slack  Flow time  Late days  Job 1 20255200 Job 2 ‾152053515 Job 3 ‾71694226 Job 4 ‾2550256717 Job 5 ‾313329865 Job 6 ‾435512141‾86‾ Total 403209 Average 67.1734.83\begin{array}{|l|c|c|l|c|c|c|}\hline \text { FCFS } & \text { Time } & \frac{\text { Due }}{\text { Date }} & & \text { Slack } & \text { Flow time } &\text { Late days } \\\hline \text { Job 1 } & 20 & 25 & & 5 & 20 & 0 \\\hline \underline{\text { Job 2 }} & 15 & 20 & & 5 & 35 & 15 \\\hline \underline{\text { Job 3 }} & 7 & 16 & & 9 & 42 & 26 \\\hline \underline{\text { Job 4 }} & 25 & 50 & & 25 & 67 & 17 \\\hline \underline{\text { Job 5 }} & 31 & 33 & & 2 & 98 & 65 \\\hline \underline{\text { Job 6 }} & 43 & 55 & & 12 & \underline{141} & \underline{86} \\\hline & & & & \text { Total } & 403 & 209 \\\hline & & & & \text { Average } & 67.17 & 34.83 \\\hline\end{array} FCFS  Job 1  Job 2  Job 3  Job 4  Job 5  Job 6  Time 20157253143 Date  Due 252016503355 Slack 55925212 Total  Average  Flow time 203542679814140367.17 Late days 0152617658620934.83
 Average number of jobs in system: 2.858\text { Average number of jobs in system: } 2.858 Average number of jobs in system: 2.858

 EDD  Time  Due  Date  Slack  Flow time  Late davs  Job3 716970 Job 2 15205222 Job 1 202554217 Job 5 313327340 Job 4 2550259848 Job 6 435512141‾86‾ Total 383193 Average 63.8332.17\begin{array}{|c|c|c|c|c|c|c|}\hline \text { EDD } & \text { Time } & \frac{\text { Due }}{\text { Date }} & & \text { Slack } & \text { Flow time } & \text { Late davs } \\\hline \text { Job3 } & 7 & 16 & & 9 & 7 & 0 \\\hline \text { Job 2 } & 15 & 20 & & 5 & 22 & 2 \\\hline \text { Job 1 } & 20 & 25 & & 5 & 42 & 17 \\\hline \text { Job 5 } & 31 & 33 & & 2 & 73 & 40 \\\hline \text { Job 4 } & 25 & 50 & & 25 & 98 & 48 \\\hline \text { Job 6 } & 43 & 55 & & 12 & \underline{141} & \underline{86} \\\hline & & & & \text { Total } & 383 & 193 \\\hline & & & & \text { Average } & 63.83 & 32.17 \\\hline\end{array} EDD  Job3  Job 2  Job 1  Job 5  Job 4  Job 6  Time 71520312543 Date  Due 162025335055 Slack 95522512 Total  Average  Flow time 72242739814138363.83 Late davs 021740488619332.17
 Average number of jobs in system: 2.716\text { Average number of jobs in system: } 2.716 Average number of jobs in system: 2.716  SPT ‾ Time  Due  Date  Slack  Flow time  Late days  Job 3 716970 Job 2 ‾15205222 Job 1 ‾202554217 Job 4 ‾2550256717 Job 5 ‾313329865 Job 6 ‾435512141‾86‾ Total 377187 Average 62.8331.17\begin{array}{|c|c|c|c|c|c|c|}\hline \underline{\text { SPT }} & \text { Time } & \frac{\text { Due }}{\text { Date }} & & \text { Slack } & \text { Flow time } & \text { Late days } \\\hline \text { Job 3 } & 7 & 16 & & 9 & 7 & 0 \\\hline \overline{\text { Job 2 }} & 15 & 20 & & 5 & 22 & 2 \\\hline \underline{\text { Job 1 }} & 20 & 25 & & 5 & 42 & 17 \\\hline \underline{\text { Job 4 }} & 25 & 50 & & 25 & 67 & 17 \\\hline \underline{\text { Job 5 }} & 31 & 33 & & 2 & 98 & 65 \\\hline \underline{\text { Job 6 }} & 43 & 55 & & 12 & \underline{141} & \underline{86} \\\hline & & & & \text { Total } & 377 & 187 \\\hline & & & & \text { Average } & 62.83 & 31.17 \\\hline\end{array} SPT  Job 3  Job 2  Job 1  Job 4  Job 5  Job 6  Time 71520253143 Date  Due 162025503355 Slack 95525212 Total  Average  Flow time 72242679814137762.83 Late days 021717658618731.17
 Average number of jobs in system: 2.674\text { Average number of jobs in system: } 2.674 Average number of jobs in system: 2.674

 LPT  Time  Due  Date  Slack  Flow time  Late days  Job 6 435512430 Job 5 313327441 Job 4 2550259949 Job 1 2025511994 Job 2 15205134114 Job 3 7169141125‾ Total 610423 Average 101.6770.5\begin{array}{|c|c|c|l|c|c|c|}\hline \text { LPT } & \text { Time } & \begin{array}{c}\text { Due } \\\text { Date }\end{array} & & \text { Slack } & \text { Flow time } & \text { Late days } \\\hline \text { Job 6 } & 43 & 55 & & 12 & 43 & 0 \\\hline \text { Job 5 } & 31 & 33 & & 2 & 74 & 41 \\\hline \text { Job 4 } & 25 & 50 & & 25 & 99 & 49 \\\hline \text { Job 1 } & 20 & 25 & & 5 & 119 & 94 \\\hline \text { Job 2 } & 15 & 20 & & 5 & 134 & 114 \\\hline \text { Job 3 } & 7 & 16 & & 9 & 141 & \underline{125} \\\hline & & & & \text { Total } & 610 & 423 \\\hline & & & & \text { Average } & 101.67 & 70.5 \\\hline\end{array} LPT  Job 6  Job 5  Job 4  Job 1  Job 2  Job 3  Time 43312520157 Due  Date 553350252016 Slack 12225559 Total  Average  Flow time 437499119134141610101.67 Late days 041499411412542370.5
 Average number of jobs in svstem: 4.326\text { Average number of jobs in svstem: } 4.326 Average number of jobs in svstem: 4.326