Find the sequence for the priority rules of
a. LPT
b. SPT
c. EDD
Given the table below and the fact that today is the 1st
 job  Process Time  Due Date  A 64 B 42 C 25 D 31\begin{array} { | l | l | l | } \hline \text { job } & \text { Process Time } & \text { Due Date } \\\hline \text { A } & 6 & 4 \\\hline \text { B } & 4 & 2 \\\hline \text { C } & 2 & 5 \\\hline \text { D } & 3 & 1 \\\hline\end{array} job  A  B  C  D  Process Time 6423 Due Date 4251

Priority Rules

Guidelines or criteria used to determine the sequence of jobs in a manufacturing or service context.

Process Time

The duration required to complete a specific process or operation within a workflow.

Due Date

The specified date by which a task, project, or payment is expected to be completed or received.

  • Acquire knowledge on essential dispatching criteria and their implementation in schedule management.
  • Establish the superior scheduling method based on particular performance benchmarks.
verifed

Verified Answer

JR
JustFor RedditMay 14, 2024
Final Answer :
a. ABDC
b. CDBA
c. DBAC