Asked by Normaly Valdez on May 30, 2024

verifed

Verified

Eisentrout Corporation has two production departments, Machining and Customizing. The company uses a job-order costing system and computes a predetermined overhead rate in each production department. The Machining Department's predetermined overhead rate is based on machine-hours and the Customizing Department's predetermined overhead rate is based on direct labor-hours. At the beginning of the current year, the company had made the following estimates: Eisentrout Corporation has two production departments, Machining and Customizing. The company uses a job-order costing system and computes a predetermined overhead rate in each production department. The Machining Department's predetermined overhead rate is based on machine-hours and the Customizing Department's predetermined overhead rate is based on direct labor-hours. At the beginning of the current year, the company had made the following estimates:   During the current month the company started and finished Job T272. The following data were recorded for this job:   The estimated total manufacturing overhead for the Machining Department is closest to: A)  $137,600 B)  $104,000 C)  $33,600 D)  $310,933 During the current month the company started and finished Job T272. The following data were recorded for this job:
Eisentrout Corporation has two production departments, Machining and Customizing. The company uses a job-order costing system and computes a predetermined overhead rate in each production department. The Machining Department's predetermined overhead rate is based on machine-hours and the Customizing Department's predetermined overhead rate is based on direct labor-hours. At the beginning of the current year, the company had made the following estimates:   During the current month the company started and finished Job T272. The following data were recorded for this job:   The estimated total manufacturing overhead for the Machining Department is closest to: A)  $137,600 B)  $104,000 C)  $33,600 D)  $310,933 The estimated total manufacturing overhead for the Machining Department is closest to:

A) $137,600
B) $104,000
C) $33,600
D) $310,933

Estimated Total Overhead

The anticipated amount of all overhead expenses for a specific period, used for budgeting and costing purposes.

Machining Department

A specific division within a manufacturing facility where machinery is used to process materials into finished products.

Manufacturing Overhead

All indirect costs associated with the production process of a company, such as utilities, depreciation, and salaries for management.

  • Understand the concept of job-order costing and its application in manufacturing.
  • Calculate apportioned overhead rates for distinct operational divisions.
verifed

Verified Answer

ZK
Zybrea KnightJun 03, 2024
Final Answer :
A
Explanation :
Machining Department predetermined overhead rate = Estimated overhead cost / Estimated machine-hours
= $78,400 / 8,000 machine-hours
= $9.80 per machine-hour

Actual machine-hours used for Job T272 = 1,600 machine-hours
Therefore, actual overhead cost for Machining Department = $9.80 per machine-hour x 1,600 machine-hours = $15,680

Estimated total overhead cost for Customizing Department = $59,200
Customizing Department predetermined overhead rate = Estimated overhead cost / Estimated direct labor-hours
= $59,200 / 14,800 direct labor-hours
= $4.00 per direct labor-hour

Actual direct labor-hours used for Job T272 = 2,400 direct labor-hours
Therefore, actual overhead cost for Customizing Department = $4.00 per direct labor-hour x 2,400 direct labor-hours = $9,600

Total actual overhead cost for Job T272 = $15,680 + $9,600 = $25,280

The estimated total overhead cost for both departments = $78,400 + $59,200 = $137,600.