Asked by Nazareth Valladares on Jun 20, 2024

verifed

Verified

Distributing the work load to reduce uneven concentrations of work is called _____.

A) frequency distribution
B) alignment process
C) project control
D) resource leveling
E) scope change

Resource Leveling

A project management technique used to adjust the project schedule based on resource constraints, aiming to minimize peaks and valleys in resource allocation.

  • Comprehend the critical role that allocating and leveling resources plays in project management.
verifed

Verified Answer

ZK
Zybrea KnightJun 20, 2024
Final Answer :
D
Explanation :
Distributing the work load to reduce uneven concentrations of work is known as resource leveling. This process involves analyzing the resource allocation and scheduling tasks to ensure that resources are distributed evenly. The process helps in optimizing resource utilization and reducing the risk of resource overload.