Establishing checkpoints and control mechanisms can help you manage your project by:

A) identifying and obtaining the necessary resources.
B) inserting interim deadlines.
C) identifying the individual tasks necessary to achieve the objective.
D) clarifying objectives when specific tasks are assigned.

Checkpoints

Predetermined points along a process or project timeline used to assess progress and make necessary adjustments.

Control Mechanisms

Tools or systems used to manage, command, or regulate the behavior of individuals or the operation of a system.

Interim Deadlines

Set checkpoints or due dates before the final deadline to ensure progress on a project or task.

  • Understand the significance of initial planning and the distribution of resources in managing projects.
  • Comprehend the importance of identifying and resolving problems proactively at all stages of the project.
verifed

Verified Answer

ZK
Zybrea KnightJun 10, 2024
Final Answer :
B
Explanation :
Inserting interim deadlines is a form of establishing checkpoints and control mechanisms, which helps in tracking progress and ensuring that the project stays on schedule.