A repetitive manufacturing firm is planning on level material use. The following information has been collected. Currently, the firm operates 250 days per year.
 Annual demand 22,000 Daily demand 88 Daily production 250 Desired lot size (2 hours of production) 63 Holding cost per unit per year $50\begin{array} { | l | r | } \hline \text { Annual demand } & 22,000 \\\hline \text { Daily demand } & 88 \\\hline \text { Daily production } & 250 \\\hline \text { Desired lot size (2 hours of production) } & 63 \\\hline \text { Holding cost per unit per year } & \$ 50 \\\hline\end{array} Annual demand  Daily demand  Daily production  Desired lot size (2 hours of production)  Holding cost per unit per year 22,0008825063$50 a. What is the setup cost, based on the desired lot size?
b. What is the setup time, based on $40 per hour setup labor?

Setup Cost

Expenses incurred to prepare or configure a process, machine, or system for production or operation.

Setup Time

The time required to prepare equipment, machines, or systems for a manufacturing process or production run.

Daily Production

The total amount of output produced by a company or industry in a single day, often measured to assess operational efficiency.

  • Examine the effects of initialization expenses and durations on the planning of production activities.
verifed

Verified Answer

ZK
Zybrea KnightMay 08, 2024
Final Answer :
(a) S = Q2∗H∗(1−d/p)2D\frac { Q ^ { 2 } * \mathrm { H } * ( 1 - d / p ) } { 2 D }2DQ2H(1d/p) leads to = 632∗50(1−88/250)2∗22000\frac { 63 ^ { 2 } * 50 ( 1 - 88 / 250 ) } { 2 * 22000 }22200063250(188/250) and S = $2.92
(b) Setup time = 4.38 min