Asked by Thembani VUTUZA on Jul 07, 2024

verifed

Verified

Why should a risk averse manager select one project over another when both projects generate the same NPV?

A) Because the manager prefers the project which has more variance in its cash flows.
B) Because the manager prefers the project with the higher IRR.
C) Because the manager prefers the project with less risky cash flows.
D) Because the manager prefers the project which has higher standard deviation in its cash flows.

Risk Averse

The tendency to prefer certainty over risk, where an individual opts for the investment with the least potential for financial loss.

NPV

A financial metric that calculates the total value of a project or investment by discounting future cash flows back to their present value and subtracting initial investment cost.

  • Execute computations and provide interpretations for the Net Present Value (NPV) and Internal Rate of Return (IRR) of investment projects in unpredictable environments.
  • Distinguish among projects by evaluating differences in cash flows and principles of risk aversion.
verifed

Verified Answer

KK
Kaleb KoffordJul 10, 2024
Final Answer :
C
Explanation :
A risk averse manager would prefer the project with less risky cash flows, as it reduces the potential for unexpected losses. While both projects may have the same NPV, the manager may be willing to sacrifice a slightly higher return to avoid the possibility of significant losses. Option A and D are not valid considerations as higher variance or standard deviation in cash flows indicate higher risk, which a risk averse manager would seek to avoid. Option B, while commonly used as a decision-making criterion, is not relevant in this case as the NPVs for both projects are the same.