Which of the following would be classified as an internal failure cost on a quality cost report?

A) Quality improvement projects.
B) Supervision of testing and inspection activities.
C) Debugging software errors.
D) Warranty repairs and replacements.

Internal Failure Cost

Costs incurred when a product does not meet quality standards before being shipped to the customer, including scrap, rework, and downtime.

Quality Improvement Projects

Initiatives aimed at enhancing the quality of products or services, often involving systematic efforts to eliminate issues and improve processes.

Debugging Software Errors

The process of identifying, analyzing, and correcting errors in software code to ensure its correct and efficient functioning.

  • Uncover the array of costs linked with quality, encompassing prevention, appraisal, internal failure, and external failure expenses.
verifed

Verified Answer

AC
Aaron CylerJul 12, 2024
Final Answer :
C
Explanation :
Debugging software errors would be classified as an internal failure cost, as it is a cost incurred to address a defect or error discovered during the production or testing process. A is incorrect as quality improvement projects are typically considered prevention costs. B may be a prevention cost if it involves activities to prevent defects from occurring in the first place, but it is not clear from the given information. D is classified as an external failure cost, as it involves the cost of repairing or replacing a defective product that has already been shipped to customers.