Which of the following statements is true about project size as an external attribute that contributes to project complexity?

A) Project size is an absolute concept.
B) The size of a project is determined by the context of the industry and the experience of the team executing the project.
C) When a company is executing a project that is much smaller than the company norm, it often results in schedule delays.
D) Though it seems practical, companies rarely divide large projects into smaller ones.
E) Large projects that fall outside the comfort zone of the project management team often create stress for the project, but small projects rarely do.

External Attribute

An external attribute is a characteristic or feature of an object or system that can be observed or measured without changing its internal state.

Project Size

An attribute of a project that signifies its magnitude, often measured in terms of cost, duration, complexity, or the number of resources involved.

Industry Context

The broader environmental and situational factors, including trends, challenges, and opportunities, that influence the operations and strategies of businesses within a specific industry.

  • Present the technological, internal, and external components that factor into project complexity.
verifed

Verified Answer

PS
Patrick SampleJul 10, 2024
Final Answer :
B
Explanation :
The size of a project is relative to the context of the industry and the experience of the team executing the project. What may be considered a small project in one industry can be a large project in another industry. The experience of the team also determines how well they can handle the project, making it easier or more complex for them.