To create an aggregate plan,a company must specify the planning horizon for the plan and the duration of each period within the planning horizon.
Planning Horizon
The future time period for which plans or strategies are developed, taking into consideration forecasted demands and resource availability.
Aggregate Plan
A plan that summarizes the expected production rates, workforce levels, and inventory on hand to satisfy demand over a certain period.
- Ascertain the usual planning period for aggregate planning.
- Grasp the basic conception and direct aims of aggregate planning.
Verified Answer
JD
Jevonne DesirJul 21, 2024
Final Answer :
True
Explanation :
The statement is true. The planning horizon is the length of time for which the plan is made, and the duration of each period specifies the length of time that is covered by each planning period. Together, these two factors determine the total number of planning periods in the aggregate plan.
Learning Objectives
- Ascertain the usual planning period for aggregate planning.
- Grasp the basic conception and direct aims of aggregate planning.
Related questions
The Goal of Aggregate Planning Is to ...
As Inputs into the Aggregate Plan Change,managers Do Not Need ...
The Operational Parameter Concerned with the Number of Units Completed ...
Breaking an Aggregate Plan into Separate Plans for Each Product ...
Short-Term Production Serves as a Broad Blueprint for Operations and ...