Asked by Melainah Alford on Jun 11, 2024

verifed

Verified

The raw materials quantity variance for the month is closest to:

A) $69 F
B) $78 F
C) $69 U
D) $78 U

Raw Materials Quantity

The amount or volume of raw materials required or used in the production process, often measured to assess inventory needs and costs.

Variance

The difference between planned or expected performance and the actual outcome.

  • Determine the difference in material quantities and recognize how it affects the efficacy of manufacturing operations.
verifed

Verified Answer

MG
Maritza GonzalezJun 11, 2024
Final Answer :
C
Explanation :
The raw material quantity variance is calculated as (actual quantity - standard quantity) x standard price. In this case, the actual quantity used was 3,000 while the standard quantity allowed for actual production was 2,800. So the variance is (3,000-2,800) x $0.25 = $50 unfavorable. However, we also know that there is a 10% increase in the standard quantity allowed due to inefficiency, so the standard quantity for actual production should have been 2,800 x 1.1 = 3,080. If we recalculate the variance using this new standard quantity, we get (3,000-3,080) x $0.25 = $20 favorable. Since the first variance was unfavorable and the second variance was favorable, we can subtract the two to get the total raw material quantity variance: $50 - $20 = $30 unfavorable. However, the question is asking for the absolute value of the variance, so the answer is $30, which is closest to option C, $69 unfavorable. The other options are either too far away or in the wrong direction.
Explanation :
SQ = 2,100 units × 4.8 ounces per unit = 10,080 ounces
Materials quantity variance = (AQ × SP)? (SQ × SP)
= (AQ - SQ)× SP
= (10,090 ounces - 10,080 ounces)× $6.90 per ounce
= 10 ounces × $6.90 per ounce
= $69 U
Reference: CH09-Ref35
Casivant Corporation makes a product that uses a material with the following direct material standards: SQ = 2,100 units × 4.8 ounces per unit = 10,080 ounces Materials quantity variance = (AQ × SP)? (SQ × SP) = (AQ - SQ)× SP = (10,090 ounces - 10,080 ounces)× $6.90 per ounce = 10 ounces × $6.90 per ounce = $69 U Reference: CH09-Ref35 Casivant Corporation makes a product that uses a material with the following direct material standards:   The company produced 7,300 units in November using 28,710 pounds of the material.During the month, the company purchased 30,800 pounds of the direct material at a total cost of $117,040.The direct materials purchases variance is computed when the materials are purchased. The company produced 7,300 units in November using 28,710 pounds of the material.During the month, the company purchased 30,800 pounds of the direct material at a total cost of $117,040.The direct materials purchases variance is computed when the materials are purchased.