The labor efficiency variance for March is:

A) $3,040 U
B) $3,685 U
C) $3,685 F
D) $3,040 F

March

The third month of the year in the Gregorian calendar, often associated with financial and performance reporting for the first quarter.

  • Learn the techniques for determining and examining labor efficiency disparities.
verifed

Verified Answer

SF
Steve FarinaMay 03, 2024
Final Answer :
C
Explanation :
SH = 2,400 units × 0.5 hours per unit = 1,200 hours
Labor efficiency variance = (AH − SH)× SR
= (1,090 hours − 1,200 hours)× $33.50 per hour
= (-110 hours)× $33.50 per hour
= $3,685 F