Asked by Raisa Anjum on Jul 25, 2024

verifed

Verified

The following data pertain to an investment:  Cost of the investment $18,955 Life of the project 5 years  Annual cost savings $5,000 Estimated salvage value $1,000 Discount rate 10%\begin{array} { | l | l | } \hline \text { Cost of the investment } & \$ 18,955 \\\hline \text { Life of the project } & 5 \text { years } \\\hline \text { Annual cost savings } & \$ 5,000 \\\hline \text { Estimated salvage value } & \$ 1,000 \\\hline \text { Discount rate } & 10 \% \\\hline\end{array} Cost of the investment  Life of the project  Annual cost savings  Estimated salvage value  Discount rate $18,9555 years $5,000$1,00010% The net present value of the proposed investment is:

A) $3,355.
B) $621.
C) ($3,430) .
D) $0.

Discount Rate

The interest rate used to discount future cash flows to their present value, reflecting the time value of money.

Annual Cost Savings

The reduction in total costs achieved on an annual basis through efficiency improvements, cost-cutting measures, or operational changes.

Investment Cost

The total amount of money spent on acquiring or investing in assets, including initial setup, purchasing, and any other related costs.

  • Utilize net present value (NPV) and internal rate of return (IRR) calculations for the assessment of investment opportunities.
  • Conceive the significant role of the discount rate in the determination of the time value of money.
verifed

Verified Answer

VB
viktoriya belinskayaJul 25, 2024
Final Answer :
B
Explanation :
The net present value (NPV) of the proposed investment is calculated by discounting the cash flows (both inflows and outflows) back to their present value using the given discount rate of 10%. The cash flows include the initial investment, annual cost savings, and the salvage value at the end of the project's life. The NPV calculation involves subtracting the initial investment from the sum of the present values of all future cash flows. The correct answer indicates that the NPV calculation was performed accurately, taking into account the specifics provided, such as the cost of the investment, life of the project, annual cost savings, estimated salvage value, and the discount rate.