Asked by Shakira Robertson on May 13, 2024

verifed

Verified

Ronda Manufacturing Corporation uses a standard cost system with machine-hours as the activity base for overhead.Last year, Ronda incurred $840,000 of fixed manufacturing overhead and generated a $42,000 favorable fixed manufacturing overhead budget variance.The following data relate to last year's operations: Ronda Manufacturing Corporation uses a standard cost system with machine-hours as the activity base for overhead.Last year, Ronda incurred $840,000 of fixed manufacturing overhead and generated a $42,000 favorable fixed manufacturing overhead budget variance.The following data relate to last year's operations:   What amount of total fixed manufacturing overhead cost did Ronda apply to production last year? A) $837,900 B) $840,000 C) $926,100 D) $972,405 What amount of total fixed manufacturing overhead cost did Ronda apply to production last year?

A) $837,900
B) $840,000
C) $926,100
D) $972,405

Fixed Manufacturing Overhead

The set amount of costs for production that do not vary with the level of output, such as salaries of supervisors and rent of the factory building.

Budget Variance

The financial difference between the budgeted amount and the actual amount spent or received.

Standard Cost System

An accounting method that assigns preset costs to products and services, which are then compared to actual costs incurred.

  • Employ conventional cost systems to determine the manufacturing overhead applied.
verifed

Verified Answer

JE
Jheri ElliottMay 19, 2024
Final Answer :
B
Explanation :
Since the fixed manufacturing overhead budget variance is favorable, it means that the actual fixed manufacturing overhead cost incurred is less than the budgeted fixed manufacturing overhead cost. Therefore, the total fixed manufacturing overhead cost applied to production should be equal to the budgeted fixed manufacturing overhead cost, which is $840,000.
Explanation :
Budget variance = Actual fixed overhead - Budgeted fixed overhead
$42,000 F = $840,000 - Budgeted fixed overhead
-$42,000 = $840,000 - Budgeted fixed overhead
Budgeted fixed overhead = $840,000 + $42,000
Budgeted fixed overhead = $882,000
Fixed component of the predetermined overhead rate = $882,000 ÷ 21,000 MHs = $42 per MH
Fixed manufacturing overhead cost applied to production = 20,000 MHs × $42 per MH = $840,000